17.1 Other non-current assets

(in PLNm) As at December 31, 2022 As at December 31, 2021
Advances for property, plant and equipment 615 749
Cost to acquire customers 102 106
Other non-current assets 133 18
TOTAL OTHER ASSETS 850 873

The calculations for property, plant and equipment under construction mainly relate to the modernisation of the Porąbka-Żar pumped storage plant by PGE Energia Odnawialna S.A., the construction of two gas and steam units by PGE Gryfino 2050 sp. z o.o. and investments made in the district heating segment. Customer acquisition costs relate to the co-financing by PGE Energia Ciepła S.A. of investments in the development of district heating networks and agency commissions at PGE Obrót S.A. Other non-current assets mainly include advance payments for CO2 deliveries.